Organization : Tenaga Nasional Berhad
Type of Facility : Apply For Electricity
Country: Malaysia
Website : http://www.tnb.com.my/residential/open-or-close-account.html
Apply Online : http://tnb.com.my/online-customer-service.html
How To Apply For TNB Electricity?
Open an Account:
An account is opened when customer applies for electricity.
Related / Similar Facility : TNB Bill Online Payment Malaysia
TNB Electricity Application Based on Load:
All new and upgrading of electricity applications are classified into two (2) categories.
1) Electricity Application for Load up to 100kVA (<100kVA):
Customers need to appoint an Electrical Contractor registered with the Energy Commission to apply electricity on their behalf.
2) Electricity Application for Load exceeding 100kVA (>100kVA):
Customers need to appoint an Electrical Consultant Engineer registered with the Board of Engineers Malaysia to apply electricity on their behalf.
Customers may download the Electricity Supply Application Handbook (ESAH) for more details on supply application process and requirements. For further clarification or more information on load requirements with regards to their premises, customers may contact any registered electrical contractor from the Energy Commission Electrical Contractors list.
Application Process: Load up to 100kVA (<100kVA)
In general, for a single (1) phase or a three (3) phase low voltage system, the load requirement for a typical residential premise is less than 100kVA.
The premise status, whether it is a newly built or an existing one, dictates the supply application process.
1) Newly Built Premise:
For a newly built premise and has no electricity supply, the process is as mentioned.
Appoint Contractor:
** Appoint Electrical Contractor from the Energy Commission Electrical Contractor list.
** The appointed Electrical Contractor shall submit the electricity application form (Domestic or Non-Domestic) together with the required documents to TNB
Fill Up Form:
** Customer fills the electricity application form and attach together the required documents.
** Customer signs the electricity supply contract (electricity application form) with TNB
Pay Essential Charges:
** TNB comes up with the connection charges relevant with the electricity connection
** Customer pays the connection charges and RM10 stamp duty
Get Electricity Supply:
** Customer pays the electricity deposit
** TNB installs meter and connects supply
Note:
Currently under this category, customers are required to pay upfront all these essential charges which include the Connection Charges, Stamp Duty and Security Deposit to apply for electricity.
To get the best deal among the listed contractors, customers are advised to liaise and request for quotations prior to appointing one.
2) Existing Premise:
Customer may apply direct to TNB without appointing a contractor for an existing premise (premise with prior electricity connection but has been disconnected).
Fill Up Form:
** Customer fills the electricity application form (Domestic or Non-Domestic) and attach together the required documents.
** Customer signs the electricity supply contract (electricity application form) with TNB
Pay Essential Charges:
** TNB comes up with the connection charges relevant with the electricity connection
** Customer pays the connection charges and RM10 stamp duty
Get Electricity Supply:
** Customer pays the electricity deposit
** TNB installs meter and connects supply
Exceptions:
Customers can only opt for this method provided:
** Premise supply has been disconnected for a period of less than 6 months (<6 months).
** TNB service cable and the premise meter board are present and in good condition.
** No premise renovation has been done involving the internal wiring.
** Customer gives assurance that the premise Internal wiring is in a good working condition.
According to Electricity Act 1995, customers are advised to get their premise internal wiring inspected by a registered electrical contractor if they unaware of the wiring condition and also as a precautionary measure.
It is the responsibility of the appointed contractor to trace the wirings (fill up Form G), test each wiring circuits (fill Form H) and then declare the results to customers.
The process of applying through contractor is as mentioned in the Newly Built Premise application process.
Customer must declare their premise installation condition truthfully, as disparity from declaration may result in supply application being rejected.
For more understandings on the safety for Electrical Wiring in Residential Building please log into www.st.gov.my and https://www.electricalsafetyfirst.org.uk/
Where to apply for Electricity?:
1) Application at TNB Kedai Tenaga nearest to your premise:
Depending on the supply application type, customers or their appointed contractor may submit the electricity supply application to the nearest Kedai Tenaga.
2) Application On-Line:
Customer may apply for electricity by filling in the e-form and appoint electrical contractor on-line. This service is applicable to:
** Individual (Residential Category) Customers
** TNB Registered Electrical Contractors
** Housing Developers
Benefits of Applying On-line:
** Application forms can now be completed online
** Faster application process at Kedai Tenaga
** Online Electrical Contractor selection and appointment
** Real-time supply application status updates
** Check amount of Connection Charges and Supply Deposit
** Mass promotion of Registered Contractors to TNB’s new customers
** Efficient and faster way to complete Group Supply Application forms
Start apply via e-Application:
Note: Due to legal restrictions, contractual documents will need to be signed off manually. Therefore, customers/contractors are reminded to submit the application form and relevant documents to the Kedai Tenaga nearest to your new premise.
View Comments (1)